On December 1st, the last correction coil (CC) conductor was completed and delivered to the next-chain producer--CC coil group, marking China’s completion of all CC conductors.
According to RO Mr QIN Jinggang,the cabling, jacket examinations and jacketing were all conducted in ASIPP, and the manufacture and delivery meet ITER Organization’s planning schedule and quality requirement.
CC conductor includes 20 conductors, two of which are qualification conductors. The total length is about 11.5 km. With the support from ITER Organization, CNDA, the Applied Superconductivity Division of ASIPP developed the manufacturing technology with domestic cooperation partners, completed the industrial production certification, established and realized a quality management and process control system which meets French nuclear requirement.
CC conductor Milestones:
August 2011 First CC conductor sample (CCCN2) passed test at SULTAN
July 20th, 2012 First CC conductor delivered to IO
April 15th, 2014 Last CC conductor short sample (CCCN5) tested at the SULTAN
CC Conductor (Left: Conductor Geometry; Right: completed Last CC conductor)
Witness of CC Conductor Final Delivery